| 单词 | Late completion |
| 释义 | 逾期完工 In building law, a failure by the contractor to achieve practical completion by the stipulated date in the building contract. Late completion is a breach of contract, which gives rise to an entitlement to damages, which is often in the form of liquidated and ascertained damages, and may give rise to a right in the proprietor to terminate the building contract: Westminister Properties Pty Ltd v Comco Constructions Pty Ltd (1990) 2 WAR 335. See also Breach of contract; Building contract; Liquidated Damages; Practical completion; Proprietor; Time stipulation. 就建築法,承建商沒有按建築合約上的指定日期,達致實際竣工。逾期完工乃一項違約,非違約方有權要求損害賠償,通常為定額或預定損害賠償,並可能導致所有人有權終止該建築合約:Westminister Properties Pty Ltd v Comco Constructions Pty Ltd (1990) 2 WAR 335。另見 Breach of contract; Building contract; Liquidated Damages; Practical completion; Proprietor; Time stipulation。 |